Project overview
The Libélula BESS is one of the largest battery storage systems in central Chile: 203 MW / 1,034 MWh in 208 lithium containers, with five hours of discharge and an investment of US$219 million in the BESS alone. It is part of Engie’s Libélula solar complex, between Colina and Tiltil, and began commercial operation in 2026.
Our contribution
For Metlen, Ecomundo manufactured the precast concrete foundations that support the BESS equipment. The pieces are produced in our plant under dimensional control and arrive on site ready to install, reducing schedules, concrete work on site and construction risks.
Highlights
- Plant-manufactured foundations, with controlled quality and dimensions.
- Fast installation straight from the truck with a crane and spreader beam, with no on-site curing.
- Replicable solution for new energy storage projects.
On-site installation
Key project figures
Let’s build the future together